In case you missed the previous days, you can find the links below:
Day 1: Removal of Kitchen Cabinets, Kitchen Base, Ceramic Tiles, and Electric Sockets
Day 2: Electrical Wall Schisms, Plaster Board Creation, Switch Boxes Installation
Day 3: Finishing With Plaster Boards and the Ceramic Tiles Installation
Everything is moving as it should be! It makes our clients happy, which in turn makes us happy.
Today we managed to finish with the installation of all the ceramic tiles on the floor, fill the joints with grout, and also finish with the plasterboardsโ plastering. On Monday, we will start installing the kitchen cabinets.
Below you can find the progress of the day:
ฮฮปฮฑ ฯฮฑ ฮบฮตฯฮฑฮผฮนฮบฮฌ ฮบฮฑฮน ฮฑฯฮผฮฟฮฏ ฮญฯฮฟฯ
ฮฝ ฯฮฟฯฮฟฮธฮตฯฮทฮธฮตฮฏ, ฮบฮฑฮน ฮณฮฏฮฝฮตฯฮต ฯฮฟ 2ฮฟ ฯฮญฯฮน ฯฯฮฟฮบฮฑฯฮฏฯฮผฮฑฯฮฟฯ. #10daysonly http://t.co/D3c92MRu5E pic.twitter.com/5pKztqUC5W
— GNicolaou LTD (@GNicolaouLTD) March 29, 2014